SLEX Alabang southbound entry re-opens earlier

Less than two weeks after it was closed on May 28, San Miguel Corporation’s SLEX Alabang Southbound Entry reopened on June 7—eight days ahead of schedule.The toll plaza entry was closed to enable SLEX contractors to undertake bored piling works for the resumed construction of the Skyway Extension Project.

 

San Miguel South Luzon Tollway Corporation
SLEX Alabang SB Entry Reopens Ahead of Schedule

 

To hasten completion of the bored piling works while maintaining quality, SMC, through its contractor, EEI, used two rigs instead of just one. Workers who returned to work also had more leeway to move on the construction site since Metro Manila was still in quarantine.

“We want to assure the motoring public and government that the Skyway Extension Project will be finished at the soonest possible time. This is to demonstrate our commitment to continue to improve our facilities and services—no matter what the situation or circumstance is,” SMC president and COO Ramon S. Ang said.

Do you want to know how to help local farmers? Visit any Petron gas station with the new kadiwa store. Click here to see the list.

 

 

Eli

Eli has 28 years of extensive IT sales expertise in Data, voice and network security and integrating them is his masterpiece. Photography and writing is his passion. Growing up as a kid, his father taught him to use the steel bodied Pentax and Hanimex 135mm film and single-direction flash, Polaroid cameras, and before going digital, he used mini DV tape with his Canon videocam. He now shoots with his Canon EOS 30D. Photography and blogging is a powerful mixture for him.
Back to top button